Power of Siberia pipeline construction works are in progress

- Underwater pipeline across the Amga River – construction and installation works completed;
- Underwater pipeline across the Aldan River – shore cutting and underwater trench digging in progress;
- Underwater pipeline across the Lena River – loosening and shore cutting in progress;
- Underwater pipeline across the Tuolba River – construction and installation works completed;
- Underwater pipeline across the Chulma River – the main pipeline run has been welded together, tested and insulated; trenching in progress;
- Underwater pipeline across the Giluy River-2 – pipeline has been welded together, tested and insulated; trenching in progress